Public calculator
Pipe Price Predictor
Estimate pipe supply price by material category using pipe weight, raw steel basis, and coating-based conversion factors.
Output
Coating factorMedian factor
Your realistic working number for negotiation and planning.
-
- Finished Rs/kg
- -
- Rs/m
- -
- Total Rs
- -
P90 factor
Your safety-margin number for budget approval.
-
- Finished Rs/kg
- -
- Rs/m
- -
- Total Rs
- -
Upload Excel BOM
Upload one or more piping BOMs in .xlsx, .xls, or .csv format.
Download the Excel template, complete the pipe details, then upload it below.
Supported column names
Size / NPS / DN, Sch/Thck/Rating or Thickness, Quantity or Length, UoM, Coating, Material, Raw Steel Rs/kg, Estimate Factor Override. Schedule text like S-STD, STD, HVY, Heavy, SCH 40, S-80, and 5S is converted to mm.
Multi Size Estimate
Add each pipe size from the input panel to build one combined estimate.
| Action | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| No pipe lines added yet. | |||||||||||
Material Category Review
Categories are detected from ASTM piping material specification data. Non-CS estimates use the same factor-based method and are indicative only.
Show Material Category Review
Upload a BOM or add pipe lines to view category-wise tables.
What-if Analysis
Compare how the estimate changes when raw steel rate, estimate factor, or coating assumption changes.
Show What-if Analysis
Add pipe lines or enter one estimate to view what-if analysis.
| No what-if scenarios available yet. | |||||||
What-if Analysis varies raw steel rate by +/-10% and +/-20%, estimate factor by +/-10% and +/-20%, and coating assumption between Yes and No. Results are indicative and intended for budget risk review.
BOM Group Review
Uploaded BOM items are grouped as Pipe, Fitting, Flange, Valves, Bolt, Gasket, Trap/Strainer, and Other.
Show BOM Group Review
Upload a BOM to view group-wise item tables.
Audit Trail
Weight Method
Pipe mass formula: W = 0.0246615 x (OD - t) x t.
- W = pipe mass in kg/m.
- OD = actual outside diameter in mm from the built-in OD table.
- t = wall thickness in mm entered by the user.
- Total weight = W x length in meter.
Price Method
- Raw steel Rs/kg is selected by year unless the user enters Raw Steel Rs/kg Override.
- Finished Rs/kg = raw steel Rs/kg x estimate factor.
- Rs/m = finished Rs/kg x pipe kg/m.
- Total Rs = Rs/m x pipe length.
Factor Method
- Coating Yes normal factor = 2.30 and P90 factor = 3.80.
- Coating No normal factor = 1.80 and P90 factor = 2.70.
- If Estimate Factor Override is entered, it replaces the normal factor.
- P90 is recalculated using the default P90-to-normal factor ratio.
Material Category Basis
- Material categories are detected from astm_piping_material_specification_webapp.json.
- The same factor-based method is used across categories in this version.
- Validate SS, alloy, duplex, and non-ferrous rates with supplier quotations.
Coating Definition
- Internal coating means epoxy lined.
- External coating means PE coated, or polyethylene coated.
- Select Coating = Yes for internal coating, external coating, or both.
Reviewer Override Check
This report is an indicative material supply estimate, not a vendor quotation. Final pricing should be validated against supplier quote, taxes, freight, testing, coating scope, delivery terms, and commercial conditions.
Method Used In This Review Version
Weight is calculated using ASME-style pipe mass formula.
W = 0.0246615 x (OD - t) x t
- W = pipe mass in kg/m
- OD = actual outside diameter in mm
- t = wall thickness in mm
Price is estimated as raw steel price multiplied by the coating-based finished-pipe conversion factor.
If Estimate Factor Override is entered, it replaces the normal estimate factor. The P90 factor is recalculated using the default P90-to-normal factor ratio.
For this calculator, select Coating = Yes when the pipe has internal epoxy lining, external PE coating, or both. Internal coating means epoxy lined. External coating means PE coated, or polyethylene coated.